Funded By Ryde City Council. This project included the removal of the existing failing 300LM of stone seawall and replaced it with approximately 7000 sandstone logs side-by-side on a basalt subbase footing with sandstone rock amour. The construction period was six months and included the supply and installation of approximately 7000 sandstone logs, 1000Tns of basalt, salt marsh conservation and replanting, detailed civil hydraulic works, path works, kerb and gutter works and landscaping.